Mare Island Bridge Construction (ongoing)

The Mare Island West Approach replacement project will begin early July 2015. This project will replace a 50-foot section of original timber-trestle
In order to maintain one way traffic coming onto Mare Island, this project
will be carried out in two stages.

Anticipated Project Milestones:
Construction begins: July 6, 2015 (one-way traffic on bridge)
Stage 1 - Closed (9 a.m. to 6 p.m.): 3-5 days in August 2015
Stage 1 - Complete: September 2015
Stage 2 - Closed (9 a.m. to 6 p.m.): 1-3 days in October 2015
Stage 2 - Complete: December 2015
Project Substantial Completion January 2016

View the full Press Release on the City of Vallejo website.